Beginning Sunday, May 15th, Highway 390 will switch to nighttime operations. Construction will halt on May 20th and 21st, and paving will begin on Sunday, May 22nd. Weather dependent, the first lift of structure is scheduled to go down from CR389 to Transmitter Road by May 29th. We will keep this page updated as new information comes in. Thank you for your patience.